MINUTES OF THE MEETING OF THE JUSTICE CENTER COORDINATING COMMITTEE AT
THE HEALTH AND HUMAN SERVICES BUILDING, 855 SOUTH DUBUQUE STREET, IOWA CITY,
IOWA:
AUGUST 5, 2009
Justice
Center Coordinating Committee Coordinator Bob Elliott called the Justice Center Coordinating Committee to order
in the Johnson County Health and Human Services Building, 855 South Dubuque
Street, at 5:02 p.m. Members
present were: Supervisors and Chair Pat Harney, Supervisor
Supervisor Rod Sullivan said he will leave the room until the County Attorney's office confirms how many Supervisors can be present at the meeting. Sullivan left at 5:02 p.m. Executive Assistant Andy Johnson left the room to call the County Attorney's Office for a ruling.
Justice Center Coordinating Committee Coordinator Bob Elliott reported that the Facilities Subcommittee met and agreed on a recommendation for the JCCC to present to the Board of Supervisors. Johnson then returned to the meeting and said that the County Attorney's Office said a majority of the Board should not be present at the JCCC meeting. Johnson said his understanding is that Supervisors Harney and Sullivan are appointed to the JCCC, and that Supervisor Meyers is on a JCCC subcommittee. Meyers confirmed that he serves on the Facilities Subcommittee. Johnson said it would be best for Meyers to leave the meeting. Meyers left at 5:04 p.m.
Elliott said the Facilities
Subcommittee has recommended that the JCCC present a recommendation to the
Board of Supervisors on the possibility of considering a split site scenario
for the Justice Center. The Subcommittee
met on July 15, 2009, to discuss whether the possibility of a significant
financial savings from using both the downtown Courthouse site and the
Press-Citizen structure and property should be further explored. The subcommittee's recommendation, though not
unanimous, reads as follows:
"The county should initiate a competent
exploration process to deter
We suggest two possible methods for exploring
the two-site option. (1) Hiring a local
consulting (architectural/engineering) firm to review existing information and
conduct a somewhat informal independent study at a cost estimated at perhaps
$10,000 to $15,000. (2) Another could be an RFP for a firm to do the
final formal site/facilities program in two parts, with the first being a
review to determine if the split-site proposal would be cost effective.
Any review process should include
professional cost estimates for planning, design, construction, and
operation. The necessity is to provide a
clear apples to apples comparison with all potential costs and savings for each
option, including operating costs for a split facility.
The committee assumes that, if it's approved,
the Board of Supervisors has access to skilled, experienced staff to advise on
how best to plan and carry out a split-site review process."
Elliott said that the JCCC
can accept this recommendation and forward it to the Board of Supervisors, can
reject the recommendation entirely, or can make another recommendation to the
Board. He then invited comments from Committee
members.
County Sheriff
Supervisor Pat Harney said
the issue boiled down to whether to further study the PC site or just the
Courthouse or to hire someone to evaluate the Courthouse and PC site on an
equal basis, apples to apples. If a $5
or $6 million savings can be realized by utilizing the PC site, then it must at
the least be considered. Pulkrabek said
that he wanted to be sure the recommendation is clear to the Board. Kempf said operational cost differences between
a split facility and a single site will be evaluated. Sixth Judicial Court Ad
County Bar Association
Representative Jim McCarragher said he is opposed to the split facilities and
noted numerous reasons. One concern is
how the cost comparison will occur, especially since others have indicated that
the Durrant Report has shortco
McCarragher said that Johnson
County appears to be moving towards localizing services to a campus-like
facility and McCarragher thinks splitting the facilities is the wrong move for
the County at this time. Efficiency will
be compromised with a split facility. He
said that this committee has spent six years studying, and the Board has
already approved a single facility downtown.
He emphasized his concern that a fair comparison be made between the
alternatives to deter
Pulkrabek said some have
already had a preli
Harney addressed
McCarragher's comments about the six-year work effort, saying that time was spent
evaluating whether the County needs a new Jail and Justice Center. The JCCC's recommendation is to have another
professional look at this. The current
price tag on the Durrant Study solution is $70 to $80 million, which is more
than the taxpayers would be willing to support.
He too, personally favors the single structure downtown and agrees that
it is in the taxpayers' best interest to evaluate the PC site.
University of Iowa
Facilities Manager Larry Wilson suggested the Committee consider how much the County
can afford. He thinks the Durrant Report
spells out the long-term needs. The JCCC
is not talking about a definitive cost-estimate of a project, but rather a
comparison of two options. This
comparison must certainly be apples to apples.
McCarragher asked if the same architect does not evaluate the PC site,
what assurances are there for like comparisons.
Kempf said that is exactly why the recommendation is to have one person
look at both sites. McCarragher said
that is not what was presented. Kempf said
the architect would be expected to review the Durrant Report specifications to
ensure that the same comparisons are made.
Elliott said that from the
perspective of the Board of Supervisors, as long as the possibility of
substantial savings exists, he thinks it must at least be investigated. From that point forward, decisions will be at
the Board's discretion. Wilson stated
that it is important to remember that blocks of space are in question here and
those blocks on one site or two will be compared. He said that advantages and disadvantages of
the intangibles can only be evaluated based on individual best judgment.
Professor Emeritus John
Stratton said they need to look at the
downtown site as basically two sites, using the Courthouse block alone or
adding in the Federal parking lot that is still an unknown factor in time and
costs. He raised the question of what constitutes
sufficient savings, and said that the term is vague and debatable. He asked if $1 million, $5 million, or $13
million is sufficient. If the savings is
at the lower end, the intangibles become more significant. Furthermore, Stratton asked to what extent
the project will be cost-driven.
Sullivan added that there is public buy-in to the downtown location and
the public's opinion about the PC site is still unknown.
County Auditor Tom Slockett
said that of concern to the public is the notion of separating the two
facilities. He recalled that when the
current Jail was built, the public was promised a tunnel would be built from
the Jail to the Courthouse. That has
never happened. Slockett asked if any
thought has been given to building the Courthouse and Jail at the PC site as he
thinks there is powerful logic, including financial savings, to connecting the
two.
Harney replied saying that
Architect Jim Novak said that a combined structure is an option on the PC
site. However, the subcommittee chose to
recommend that the Courthouse be utilized as part of the project, so the
Courthouse would have to remain downtown.
Edmonson said he agrees there is merit in keeping the buildings
together. If the Courthouse is moved to
the PC site, then his understanding is that in Johnson County, there is a lot
of support for continuing use of the Courthouse and the Committee will need a
rational plan for its use. Edmonson said
the District Court's preference is to keep the facility downtown, but he agrees
it is reasonable to at least evaluate the PC site. Pulkrabek said that a pressing concern is to
lower the cost of the project, and splitting the facility might address those
concerns.
Public Defender John
Robertson said he hopes it goes without saying that a combined facility centrally
located downtown is the preference. It
will be very difficult to calculate cost savings from an off-site jail. The value of the intangibles has to be
calculated, and if significant cost savings trump those intangibles, then the
public is entitled to know that. His
opinion is that opposition to the project is inevitable, and will be compounded
if the public learns an alternative with significant savings was not
investigated by the Board. Robertson
said there is a fundamental disadvantage in a system where client/attorney
meetings and communications are logistically inconvenient or challenging. There are significant intangible values in
keeping clients and personnel easily accessible. Finally, Robertson said any study of the PC
site must involve polling of the neighborhood as he predicts tremendous
resistance from the residents in affluent housing developments adjacent to the
PC property.
Elliott said the Board of
Supervisor's are very aware that the community will demand that the Courthouse
not only be retained, but also used and maintained. Sullivan said everything has its cost. He asked if a $20 million savings can be
realized with a combined facility at the PC site, does that change public
opinion about the use of the Courthouse.
Slockett said he entirely agrees that the public will want to continue
using the Courthouse. The Courthouse was
originally designed as a
Kempf said his preference is
for a combined facility downtown, but Stratton was right when he said that
"significant savings" is going to be debatable. Sullivan said he wants to add to the
recommendation that whatever location is selected, the building plans must
include options for expansion to the Jail and the Courthouse.
Harney said that he has not
received any negative comments or resistance to the PC site, and has instead heard
from supporters. The location near
Interstate-80, and with accessibility to
Elliott recommended polling
the JCCC members to deter
Johnson agreed to contact
all JCCC members as soon as a date is selected for the committee to present
their recommendation to the Board.
Adjourned at 5:55 p.m.